|    | 
          | 
      | 
  
   
    |       | 
                   
    Laying Instructions for Floor  | 
  
   
    (A) 
        SUBSTRATE PREPARATION - FLOOR 
      
        - The ground 
          is to be watered and rammed thoroughly to create a firm base. 
 
        - Over this 
          3” of river sand is to be laid and rammed thoroughly.
 
        - On top 
          of the sand cushion, for pedestrian traffic, 4” of 1:5:10 brick 
          jelly concreting has to be done. For heavy traffic, 4” of 1:4:8 
          PCC concreting to be done.
 
         
       
      (B) 
        FLOOR TILES LAYING 
      
        - Prepare 
          base mortar with cement and sand in the ratio 1:4. 
 
        - The 
          total mortar thickness should not be more than 1”. In case where 
          tiling is to be done on RCC slabs, finished floor levels would have 
          to be marked using tube levels. In this process, if it is observed in 
          some areas mortar thickness is likely to be in excess of 1”, in 
          those areas PCC work will have to be done to raise levels, so that mortar thickness 
          is not more than 1”.
 
        - Set 
          the levels for the finished floor (i.e., dead level or slope as specified 
          by the Architect / Contractor).
 
        - Prepare 
          cement slurry (i.e. mixture of cement and water to form a thick paste) 
          and spread it on the levelled base mortar.
 
        - Wet 
          the reverse of the tile with water. Complete immersion of tile in water 
          is not required.
 
        - If 
          tiles are square or rectangular in shape, set the right angles for the 
          rooms and place the first tile along the right angle lines and place 
          it on base mortar. Tap gently and uniformly only with a rubber or wooden 
          mallet covered with cloth to obtain perfect levels.
 
        - Clean 
          the surface of the tile with a wet sponge immediately after laying. 
          Ensure that the base mortar cement which squeezes through joints does 
          not settle on the tile. Also ensure that the water used is clean and 
          not salty, hard or brackish.
 
        - It 
          is suggested to leave a fine gap of 1mm all round for external tiles 
          like Regalia, Aquarius, etc. for fast and proper laying.
 
        - For 
          the tiles like Macedonia, Marmara, Basel and Magnifique, offset 
          laying shall be followed.
 
           
          a) 
          While placing Macedonia, a groove of 6-8 mm must be 
          left all around the tile.  
           
          b) In the case of Basel, the second tile should be 
          placed exactly at the bottom of the first diamond and ensure the grooves 
          match perfectly. 
           
           
          c) Likewise, when following offset laying for Magnifique, 
          Marmara the second tile should be placed exactly at the mid point of the other 
          tile.  
           
          d) For Napoli & Figaro it is recommended that it be laid with Senora or if laid by itself, then to follow offfset laying pattern. 
         
        - For 
          external tiling completely open to sky, the tiles should be laid in 
          such a way that for every 10’x10’ area laid, there should 
          be an expansion gap of 2mm on all sides. This should be followed throughout 
          the area of laying, to provide for the expansion, for all tiles. Absence 
          of expansion gaps may result in lifting / chipping / cracking of tiles.        
 
        - In 
          site where multiple levels are encountered, the tiles on the ridge will have to be adequately protected with mortar 
          cushion.
 
        - When 
          large span tiles are laid on curved substrate, it is suggested that 
          the tiles be cut to take the contour of the slope ensuring proper bedding.
 
        - Fill 
          in the joints with pointing material which is a mixture of white cement 
          and desired colour of pigment. To arrive at the desired colour/shade, 
          mix the same with water to form a smooth paste which should be applied 
          to the joints preferably with the use of rubber squeeze or rubber sheet. 
          For higher quality of finishes, you could use, if required, a polymer 
          based cementitious tiling joint filler. Do not apply the pointing material 
          all over the tile surface.
 
        - Allow 
          pointing material to set, for 15 minutes and then clean the surface 
          of the tile with wet sponge, removing the excess pigment on the tile 
          surface.
 
        - Wash 
          the surface with soap water or mild detergent to obtain a clean surface.
 
        - Do 
          not use the area laid for 3 days for pedestrian traffic areas 7 days for light traffic areas and 10 days for heavy traffic areas. 
 
        | 
  
   
    |    
         
    
  | 
  
  
  
    |   |  
    Laying Instructions for Walls | 
  
  
    |   |  
    
        - Ensure adequate roughage on the wall before application of mortar, especially if it is an already painted wall, which is to be tiled now.
 
        - Plaster 
          the surface to be tiled with mortar (cement and sand ratio 1:3).
 
        - Prepare 
          cement slurry (i.e. mixture of cement and water to form a thick paste) 
          and spread it on the reverse of the tile after wetting the tile with 
          sponge.
 
        - Instructions 
          given for floor against S. Nos. 5, 6, 7, 10, 12, 13, 14 & 15 of floor 
          tiles laying should be followed.
 
       
        Stacking 
    Guidelines  | 
  
  
    |   |  
     
       1. All 
        fully covered closed boxes like Monolisa and other closed tile boxes to 
        be stacked horizontally only, upto a height of 6 boxes one on top of the 
    other.   | 
      | 
    2. 
      Larger tiles packed like Macedonia, Babylon, Enchante / Espana with one side covered or otherwise, to be 
      only vertically stacked, Maximum 2 boxes height. | 
      | 
  
  
    |   |  
    3. 
      All designs in shrink wrapped packages are to be only vertically stacked upto 6 boxes high. | 
      | 
       | 
      | 
  
  
    |   |  
      | 
      | 
  
  
    |   |  
     Before commencing Laying of Eurocon Tiles | 
  
  
    |   |  
        
        (a) If Mosaic / Marble / any other natural stone which needs machining and polishing is being used in any other part of your floor, it is necessary that this work is completed 
    (b) Ceiling final coat of paint, all electrical, civil and carpentry works should be completed.  | 
  
   
    |   | 
  
   
    |   
         
        Home 
        . About us . 
        Projects  . 
        Contact us .  Shade 
        Indicator . Disclaimer 
        . Design List   | 
  
   
    |   | 
  
  
   
 
       
      
	  
	  
	  
	  New Products  - Rustiques . Facilini . Scudo . GFRC & Speciality Flooring 
       
	   |